Schedule risk (Monte Carlo)

Try it

The app runs here in your browser. Nothing you type leaves it; what it saves stays in this browser, and Claude is off here. Open it on its own.

Download monte-carlo.wardian Import it in Wardian: Settings → Import.

A Wardian suite that answers "when will this project really finish?". You list the tasks, each with a best, a most likely and a worst case, and what each task waits for. The suite then runs the project 10,000 to 1,000,000 times with random durations. It shows the finish times you can promise, how they spread, and which tasks decide them.

A plan built from the most likely estimates is almost always late. In the sample project it says 35 days, and only 9% of runs finish that soon. Delays add up along a path, and where tasks run in parallel, the project waits for the slowest one.

It is a suite because it has several jobs: inputs, a simulation, three views and an export. Each part has its own panel, so you can arrange them. The simulation is heavy, so it runs in a Web Worker and the page stays responsive during a million trials.

PartSlotJobContract
tasksasideThe editable task table, the sample project, and the settings: trials, estimate shape, unit, start date, seed. It checks the list as you type and remembers it. It has Run again and a progress bar with Stop.emits project:changed (retained); listens sim:progress; needs sim.run, sim.cancel; storage
sim—Runs SimEngine in a Web Worker made with ctx.spawn from the inlined scripts (ctx.source). It reports progress about ten times a second. Each change to the project starts a new run.listens project:changed; emits sim:progress, sim:result (both retained); provides run, cancel; worker, source
forecastmainP50, P80 and P95, with dates when a start date is set. The mean ± standard deviation, and how the most-likely plan compares. A progress bar with Stop.listens sim:result, sim:progress; needs sim.cancel
histogrammainTwo SVG charts on one time axis. The top chart shows the share of trials that finish in each bin. The bottom chart is the S-curve: the chance to finish by each time. P50, P80 and P95 are marked on both. Hover over a bin, or use the arrow keys, to read it.listens sim:result
criticalmainThe criticality index of each task, highest first: the share of trials in which the task was on the critical path.listens sim:result
exportmainDownloads the percentiles (P0–P100, with dates) and the criticality table as CSV.listens sim:result; claude:downloads

How a run flows:

  1. tasks emits project:changed.
  2. After a 300 ms pause in typing, sim posts {type: 'run', project, trials, seed} to its worker.
  3. The worker runs the trials in slices of about 40 ms. After each slice it posts its progress, so a stop message can get in between slices.
  4. sim emits sim:progress. The bars in tasks and forecast show it.
  5. At the end, sim emits one sim:result. forecast, histogram, critical and export each draw from it.

Stop calls sim.cancel. The run then ends with the trials it has done so far, and every view says how many that was. The result holds summaries only (percentiles, a histogram and the criticality), never the million raw trials, so the copy that goes to each part is small.

shared/ holds what several parts use, listed in suite.json "scripts":

apps/sim/engine.js is the simulation. It has no DOM, so the same text runs in the worker, or in the sim frame when a host blocks workers. The panels then say "on the main thread".

The maths.

Limits.